โ All projects
Innovu
IGNITE ยท Innovu
Phase
Preparation
Kickoff
2026-04-27
Target close
2026-10-24
Lead
Jon Tingling
Kickoff Meetingplanned
Client due: Thu, Apr 30
1.Principal reviewJon Tingling2026-04-2912:00
2.Client sendJon Tingling2026-04-3010:00
Financial Model v1planned
Client due: Mon, May 11
1.DraftAvram Prljincevic2026-05-0417:00
2.Internal reviewZiyan Karim2026-05-0717:00
3.Principal reviewJon Tingling2026-05-0912:00
4.Client sendJon Tingling2026-05-1110:00
QofE Engagement Startplanned
Client due: Mon, May 18
1.DraftZiyan Karim2026-05-1517:00
2.Principal reviewJon Tingling2026-05-1712:00
3.Client sendJon Tingling2026-05-1810:00
Teaserplanned
Client due: Wed, May 20(baseline May 18)
1.DraftAvram Prljincevic2026-05-1117:00
2.Internal reviewZiyan Karim2026-05-1417:00
3.Principal reviewJon Tingling2026-05-1612:00
4.Client sendJon Tingling2026-05-1810:00
1 revision
2026-05-18 โ 2026-05-20by Travis K. Mahoney on 2026-05-19
Client requested extra time
CIM v1planned
Client due: Wed, May 27(baseline May 25)
1.DraftAvram Prljincevic2026-05-2017:00
2.Internal reviewZiyan Karim2026-05-2317:00
3.Principal reviewJon Tingling2026-05-2512:00
4.Client sendJon Tingling2026-05-2710:00
1 revision
2026-05-25 โ 2026-05-27cascadeby Travis K. Mahoney on 2026-05-19
Cascade: Client requested extra time
Buyer Long Listplanned
Client due: Wed, Jun 3(baseline Jun 1)
1.DraftZiyan Karim2026-05-3117:00
2.Principal reviewJon Tingling2026-06-0212:00
3.Client sendJon Tingling2026-06-0310:00
1 revision
2026-06-01 โ 2026-06-03cascadeby Travis K. Mahoney on 2026-05-19
Cascade: Client requested extra time
NDA Distributionplanned
Client due: Wed, Jun 10(baseline Jun 8)
1.Principal reviewJon Tingling2026-06-0912:00
2.Client sendJon Tingling2026-06-1010:00
1 revision
2026-06-08 โ 2026-06-10cascadeby Travis K. Mahoney on 2026-05-19
Cascade: Client requested extra time
IOIs Dueplanned
Client due: Wed, Jul 1(baseline Jun 29)
1.Principal reviewJon Tingling2026-06-3012:00
2.Client sendJon Tingling2026-07-0110:00
1 revision
2026-06-29 โ 2026-07-01cascadeby Travis K. Mahoney on 2026-05-19
Cascade: Client requested extra time
Management Presentationsplanned
Client due: Wed, Jul 15(baseline Jul 13)
1.DraftAvram Prljincevic2026-07-0817:00
2.Internal reviewZiyan Karim2026-07-1117:00
3.Principal reviewJon Tingling2026-07-1312:00
4.Client sendJon Tingling2026-07-1510:00
1 revision
2026-07-13 โ 2026-07-15cascadeby Travis K. Mahoney on 2026-05-19
Cascade: Client requested extra time
LOI Signedplanned
Client due: Wed, Aug 5(baseline Aug 3)
1.Principal reviewJon Tingling2026-08-0412:00
2.Client sendJon Tingling2026-08-0510:00
1 revision
2026-08-03 โ 2026-08-05cascadeby Travis K. Mahoney on 2026-05-19
Cascade: Client requested extra time
Buyer Due Diligenceplanned
Client due: Sun, Sep 6(baseline Sep 4)
1.DraftZiyan Karim2026-09-0317:00
2.Principal reviewJon Tingling2026-09-0512:00
3.Client sendJon Tingling2026-09-0610:00
1 revision
2026-09-04 โ 2026-09-06cascadeby Travis K. Mahoney on 2026-05-19
Cascade: Client requested extra time
Purchase Agreementplanned
Client due: Sun, Oct 11(baseline Oct 9)
1.DraftAvram Prljincevic2026-10-0417:00
2.Internal reviewZiyan Karim2026-10-0717:00
3.Principal reviewJon Tingling2026-10-0912:00
4.Client sendJon Tingling2026-10-1110:00
1 revision
2026-10-09 โ 2026-10-11cascadeby Travis K. Mahoney on 2026-05-19
Cascade: Client requested extra time
Closingplanned
Client due: Mon, Oct 26(baseline Oct 24)
1.Principal reviewJon Tingling2026-10-2512:00
2.Client sendJon Tingling2026-10-2610:00
1 revision
2026-10-24 โ 2026-10-26cascadeby Travis K. Mahoney on 2026-05-19
Cascade: Client requested extra time