โ All projects
Airtame
AIRTAME ยท Airtame
Phase
Preparation
Kickoff
2026-06-15
Target close
2026-12-12
Lead
โ
Kickoff Meetingplanned
Client due: Thu, Jun 18
1.Principal reviewโ2026-06-1712:00
2.Client sendโ2026-06-1810:00
Financial Model v1planned
Client due: Mon, Jun 29
1.Draftโ2026-06-2217:00
2.Internal reviewโ2026-06-2517:00
3.Principal reviewโ2026-06-2712:00
4.Client sendโ2026-06-2910:00
QofE Engagement Startplanned
Client due: Mon, Jul 6
1.Draftโ2026-07-0317:00
2.Principal reviewโ2026-07-0512:00
3.Client sendโ2026-07-0610:00
Teaserplanned
Client due: Mon, Jul 6
1.Draftโ2026-06-2917:00
2.Internal reviewโ2026-07-0217:00
3.Principal reviewโ2026-07-0412:00
4.Client sendโ2026-07-0610:00
CIM v1planned
Client due: Mon, Jul 13
1.Draftโ2026-07-0617:00
2.Internal reviewโ2026-07-0917:00
3.Principal reviewโ2026-07-1112:00
4.Client sendโ2026-07-1310:00
Buyer Long Listplanned
Client due: Mon, Jul 20
1.Draftโ2026-07-1717:00
2.Principal reviewโ2026-07-1912:00
3.Client sendโ2026-07-2010:00
NDA Distributionplanned
Client due: Mon, Jul 27
1.Principal reviewโ2026-07-2612:00
2.Client sendโ2026-07-2710:00
IOIs Dueplanned
Client due: Mon, Aug 17
1.Principal reviewโ2026-08-1612:00
2.Client sendโ2026-08-1710:00
Management Presentationsplanned
Client due: Mon, Aug 31
1.Draftโ2026-08-2417:00
2.Internal reviewโ2026-08-2717:00
3.Principal reviewโ2026-08-2912:00
4.Client sendโ2026-08-3110:00
LOI Signedplanned
Client due: Mon, Sep 21
1.Principal reviewโ2026-09-2012:00
2.Client sendโ2026-09-2110:00
Buyer Due Diligenceplanned
Client due: Fri, Oct 23
1.Draftโ2026-10-2017:00
2.Principal reviewโ2026-10-2212:00
3.Client sendโ2026-10-2310:00
Purchase Agreementplanned
Client due: Fri, Nov 27
1.Draftโ2026-11-2017:00
2.Internal reviewโ2026-11-2317:00
3.Principal reviewโ2026-11-2512:00
4.Client sendโ2026-11-2710:00
Closingplanned
Client due: Sat, Dec 12
1.Principal reviewโ2026-12-1112:00
2.Client sendโ2026-12-1210:00